#83 Gap of multiple of 5 days leads to wrong start date

1.5.2
open
nobody
None
6
Red_Hat_Enterprise_Linux_6
Gnone
Scheduling
Minor
2014-04-10
2014-04-08
Eric L.
No

Steps to reproduce:

  1. create a task 1 ending on a Friday at 17h00 (standard end of the day)
  2. create a task 2 of 1 day depending on task A with a gap of 5 days or a multiple (e.g. 1FS+5days)
  3. then you'll see that task 2 starts on Saturday 8h00 and ends on Monday 17h00.

Conclusion:

End time is correct, but start time is obviously wrong, it should be Monday 8h00.