Tested in versión 1.5.9
- Generate a Project. Add any tasks, resources, etc.
- Save as Baseline
- Save as Baseline1
- Go to Costs view, prepare it to see Cost, Baseline Cost and Baseline1 Cost
- Change Project, getting new costs. E.g., changing resource costs, adding new resources to task, etc.
- Save as Baseline (both cleaning first of directly overwritting it)
- Baseline1 cost is changed too...
So, baseline1 is invalidated and unuseful.